Tuas View Extension Phase 3B

  • Image 01
  • Image 02
  • Tuas View (Under Construction)
  • Tuas View (Completed)

General Description

  • The project involves Soil Improvement Works by Vibro-Compaction Method, Sewer Works (1.5m & 1.65m diameter Sewer Line) and Drainage & Road Works.

Technical Information

  • This is a fast-track project which requires detailed planning, close monitoring and substantial amount of resources so as to complete the 2.2km length of sewer, drainage and road works within the tight construction schedule of 12 calendar months. The presence of high ground water table has posed great challenges to the sewer works which involves 12m deep excavation by open cut method. Various combinations of dewatering systems have been implemented to manage the high ground water table efficiently during the sewer works.